Project Brief

Capacity 1200 MW (2X600 MW) 
Location Matarbari and Dhalghata Union in Maheshkhali Upazilla of Cox’s Bazar District. A long water course and the kohelia river on the East side, the Bay of Bengal on the West side, a homestead village of Nasir Mohammad Deil on the South side and another homestead on the North side of the project side. 
Location Data (GPS) East Longitude   : 91051’45” ~ 91053’59”ENorth Longitude : 21041’48” ~ 21042’39”E
Area 1499.80 Acre (Matarbari Union 843.08 Acre + Dhalghata Union 471.80 Acre) 
Elevation 10m + MSL for Power Block Area 
Mode of Operation Base Load 

 

Plant Type Ultra Super Critical 
Primary Fuel and Requirement Sub-bituminous imported coal having GCV of 4,200-5,000 kcal/kg and low sulfur content (1.0wt% or less) coal. Around 3.73 million tonne per annum (at 80% CF). 
Environmental Safety Measures Low NOx burner and over fire air, seawater FGD and electrostatic precipitator will be facilitated to reduce emissions and pollutions and to meet WHO standard for ambient on quantities. 
Stack Height 275m 
Water Source Sea 
Power Evacuation 400 KV Double Circuit Line 
Single Buyer Bangladesh Power Development Board 
Associated Facilities Construction of jetty and coal handling facilities for coal import, coal storage, township development and road communication.
Flash News

  • DOE has approved EIA Report of Transmission Line under RE Component
  • MOU signed Between Coal Power Generation Company Bangladesh Limited and Sembcorp Utilities Pte. Ltd., Singapore for the Implementation of Phase 1of the 2X700 MW Matarbari Coal Fired Power Project
  • DOE has approved EIA Report of Matarbari 2x600 MW Coal Fired Power Plant Project
  • CPGCBL has prepared draft Township Development Plan
  • CPGCBL has prepared draft Area Development Plan
  • Loan Agreement for Matarbari Ultra Super Critical Coal Fired Power Project Signed on 16 June 2014
  • CPGCBL has prepared draft PPA, IA 
  • CPGCBL Engaged Matarbari JVC as Consultant for Matarbari USC Coal Fired Power Project
  • Land Acquisition Completed